Grenfell

MHCLG publishes November update on Grenfell Tower deconstruction and memorial work

The Ministry of Housing, Communities and Local Government has issued its November 2026 community update on taking down Grenfell Tower, alongside dust, noise and vibration monitoring reports for 31 August to 27 September.

Timeline: 16 November 2026, Update published; 31 August to 27 September 2026, Monitoring period; September 2025, Works started; 25 August 2026, Crown development approval
Graphic: Building Safety Today

The Ministry of Housing, Communities and Local Government (MHCLG) published its November 2026 community update on the taking down of Grenfell Tower on 16 November, with monitoring reports covering 31 August to 27 September 2026.

The update sets out how the government and its contractors are taking down the Tower, and carries information on work towards a memorial and how to contact the memorial design team, the department said.

It is accompanied by dust, noise and vibration monitoring reports for the four-week period, and has been translated into 12 languages, including Amharic, Arabic, Bengali, Farsi, Somali, Tagalog, Tigrinya and Urdu.

MHCLG said it continues to share information about the Tower and to listen to bereaved families, survivors and residents in the immediate community, and that all work at the site is sensitive.

The monitoring reports

The November reports follow the October 2026 update, which carried dust, noise and vibration reports for 27 July to 30 August 2026.

The programme

The government announced on 7 February 2025 that Grenfell Tower would be carefully taken down to the ground, saying engineering advice had found the Tower significantly damaged. At that point it said the work would likely take around two years.

In a later statement on next steps, MHCLG said it intended to modify the contract of Deconstruct UK (DUK), the principal contractor for site maintenance and security. It said the earliest start for the work was September, and that it expected the work to take around two years once started.

According to the Planning Inspectorate, the works began in September 2025 under permitted development rights. The inspectorate then approved a Crown development application for the scheme on 25 August 2026, having accepted it for examination on 27 May 2026. The decision was made following a written representations procedure.

The approved development involves works to take down the Tower to ground level from its original height of 24 storeys, the inspectorate said.

The memorial

In its next steps statement, MHCLG said all materials from the Tower would be treated with the utmost respect, and that it wanted to discuss plans for a second site for materials not used in the memorial or conserved. It said it would follow the recommendation of the independent Grenfell Tower Memorial Commission in its report, Remembering Grenfell: Recommendations and next steps to a memorial, and continues to support the commission.

In a separate statement on elements of the Tower, the department said the memorial design process is being led by Freehaus. A request had been made to retain certain elements of the Tower from above floor 9, but no decisions had been taken on what would happen to those elements, including whether they would be incorporated into the memorial.

The November update includes details of how to contact the memorial design team, and the department said it continues to share information about the Tower with bereaved families, survivors and residents in the immediate community.

Sources

  1. Ministry of Housing, Communities and Local Government (opens in a new tab) (accessed 2026-11-16)
  2. Planning Inspectorate (opens in a new tab) (accessed 2026-11-16)
  3. Ministry of Housing, Communities and Local Government (opens in a new tab) (accessed 2026-11-16)
  4. Ministry of Housing, Communities and Local Government (opens in a new tab) (accessed 2026-11-16)
  5. Ministry of Housing, Communities and Local Government (opens in a new tab) (accessed 2026-11-16)
  6. Ministry of Housing, Communities and Local Government (opens in a new tab) (accessed 2026-11-16)

This story was researched from the primary sources above and checked against them before publication. Spotted an error? Tell us and we will correct it promptly.

Get stories like this every Friday

The Building Safety Today weekly: the week's the building safety regime, remediation and fire safety news in one email, free, and the TC Media Group monthly edition. Unsubscribe in one click.

By subscribing you agree to receive the Building Safety Today weekly and the TC Media Group monthly edition. We confirm your address first. Privacy.

More from Building Safety Today